§22-21-42. Review and final inspection.  


Latest version.
  • The State Board of Health shall send written review comments to the project architect within 60 calendar days for projects costing less than fifteen million dollars ($15,000,000), or within 120 calendar days on projects costing over fifteen million dollars ($15,000,000), of the State Board of Health's receipt of each submittal. If the review is not timely made, the fee as established by Section 22-21-44 and due at drawing approval shall be waived. The State Board of Health shall perform the final inspection within 30 calendar days of the receipt of a written request for inspection from the project architect or by the date requested by the project architect, whichever shall be later. If the final inspection is not timely made, the remainder of the fee shall be waived.

(Act 2000-686, p. 1393, §3.)